• About
  • Advertise
  • Subscribe
  • Contact
  • Events
Wednesday, January 14, 2026
Newsletter
SUBSCRIBE
  • News
    • Contracts awarded
    • Open tenders and opportunities
    • Events
  • Features
  • Water
  • Wastewater
  • Gas
  • Electricity
  • Civil Construction
  • Events
No Results
View All Results
  • News
    • Contracts awarded
    • Open tenders and opportunities
    • Events
  • Features
  • Water
  • Wastewater
  • Gas
  • Electricity
  • Civil Construction
  • Events
No Results
View All Results
Home Electricity Substations

Component arrival marks leap forward for EnergyConnect

by Kody Cook
October 19, 2023
in Electricity, News, Projects, Renewable Energy, Substations
Reading Time: 4 mins read
A A
Featured image: Equipment arrival at Buronga Substation. Image credit: Transgrid. 
Share on FacebookShare on Twitter

The arrival of key components for two synchronous condensers has marked a major milestone for Australia’s largest electricity transmission project, EnergyConnect. 

EnergyConnect will allow energy to be shared between New South Wales, South Australia, and Victoria and enable the connection of more new renewable generation. 

Transgrid and construction partner Elecnor Australia are building the 700km New South Wales section of the project from Wagga Wagga to the South Australian border, and a connection to Red Cliffs in Victoria. 

The 120MVAr synchronous condensers will sit at the heart of the project to help maintain voltage on the transmission network and provide system resilience services such as inertia. 

Each unit is designed to rotate at a speed of 750rpm and generate inertia of 7MWs/MVA. 

Transgrid Executive General Manager of Major Projects, Gordon Taylor, said that these condensers will play a key role keeping the grid stable as Transgrid builds the energy superhighway to make Australia’s transition to renewable energy possible. 

“Construction is powering ahead on EnergyConnect, and we are getting on with the job of delivering this national critical project, which will unlock greater renewable energy sharing between three states,” Mr Taylor said.  

“This project is a key enabler for Australia’s decarbonised future.”

Elecnor Australia Project Director, Samuel Basanta Lopez, said that the world is watching the transformation of Buronga into one of the biggest and most sophisticated substations in the Southern Hemisphere. 

“It will act as the main hub for the connection between New South Wales, South Australia and Victoria,” Mr Lopez said. 

“There has been impressive progress despite the huge engineering challenges. I’m immensely proud of what our team has achieved from the pouring of the foundations, to the steel in the synchronous condenser building, the installation of the gantry crane, and now the arrival of the synchronous condensers.”

The synchronous condensers were supplied by Andritz with components built in Austria, Spain and Brazil. They were shipped to Melbourne before a three-day road journey to Transgrid’s Buronga substation near Mildura. 

Transgrid’s Electrical Site Manager Jason Scott said that it is a huge milestone having them arrive on site and is a big step in the project moving forward. 

“The condensers will form the backbone for stability throughout the new substation,” Mr Scott said. 

“A massive logistical effort was required with four prime movers needed to transport the two lower halves of the condensers, which weigh 110t each, and the rotor units, which weigh 85t.” 

The machines will now undergo five months of commissioning and testing. 

Elecnor Australia Electrical and Installation Manager, Darren Parkinson, said that the condensers are very important to Australia’s renewable targets as the nation starts bringing new solar and wind farms onto the transmission network. 

“It’s great to be involved in something so big and complex, which makes the project extremely interesting to all the engineers and everybody on the project,” Mr Parkinson said. 

The synchronous condensers will be housed in a 60m-long, 1200m² machine hall manufactured in Geelong by Thornton Engineering. 

Delivery teams on site battled rain and high winds and worked tirelessly to install cladding on the machine hall so the condensers would be protected from the elements and dust. 

The foundations for the condensers required 1,700m³ of concrete, which had to be poured in two all-night operations. 

The machine hall includes a 130t bridge crane that played a critical role in the assembly of the synchronous condensers on site. 

The lift and installation of the equipment was achieved safely and on time thanks to collaboration between Crane Systems Australia, George Rydel, and B&M Dorrington. 

The 16ha Buronga site will be one of the most complex in the Southern Hemisphere for technology and engineering with equipment including: 

  • Five 200MVA phase-shifting transformers 
  • Four 330kV 60MVAr shunt reactors 
  • Two 120MVAr synchronous condensers 
  • Two 120MVA 330/12kV step down transformers 
  • Three 200MVA 330/220kV power transformers 
  • Two 330kV 52MVAr capacitor banks 

Featured image: Equipment arrival at Buronga Substation. Image credit: Transgrid. 

Related Posts

Image: Origin Energy

Massive battery storage system changes the future of Eraring

by Staff writer
January 13, 2026

The name of Eraring may yet become synonymous with Australia’s energy future, as it transitions away from coal-based power and...

Image: Jason/stockadobe.com

Utilities face major challenge to restore networks in bushfire areas

by Staff writer
January 13, 2026

Utilities in Victoria will face major challenges with rehabilitation as conditions ease and the mop up begins after multiple bushfires...

Screenshot

Renewables go full Tilt with second investment decision

by Staff writer
January 8, 2026

Tilt Renewables has reached a final investment decision (FID) on its second wind farm in a matter of weeks, with...

Please login to join discussion

Read our magazine

Join our newsletter

View our privacy policy, collection notice and terms and conditions to understand how we use your personal information.

Utility is the title of choice for decision makers at all levels of water and energy utilities, as well as other major players like consulting engineers and first-tier contractors. Utility is integrated across print and online, and explores the biggest news and issues across the utility industry. It is Australia’s only dedicated utility magazine, and covers all areas of the utility sector, including water and sewer, gas, electricity, communications and the NBN.

Subscribe to our newsletter

View our privacy policy, collection notice and terms and conditions to understand how we use your personal information.

About Utility

  • About
  • Advertise
  • Subscribe
  • Contact
  • Digital magazine
  • Events
  • Terms & Conditions
  • Privacy Collection Notice
  • Privacy Policy

Popular Topics

  • News
  • Water
  • Electricity
  • Projects
  • Water and Wastewater Treatment
  • Spotlight
  • Civil Construction
  • Renewable Energy

© 2026 All Rights Reserved. All content published on this site is the property of Prime Creative Media. Unauthorised reproduction is prohibited

No Results
View All Results
NEWSLETTER
SUBSCRIBE
  • News
    • Contracts awarded
    • Open tenders and opportunities
    • Events
  • Features
  • Water
  • Wastewater
  • Gas
  • Electricity
  • Civil Construction
  • Events
  • About
  • Advertise
  • Subscribe
  • Contact

© 2026 All Rights Reserved. All content published on this site is the property of Prime Creative Media. Unauthorised reproduction is prohibited