• About
  • Advertise
  • Subscribe
  • Contact
  • Events
Wednesday, July 15, 2026
Newsletter
SUBSCRIBE
  • News
    • Contracts awarded
    • Open tenders and opportunities
    • Events
  • Features
  • Water
  • Wastewater
  • Gas
  • Electricity
  • Civil Construction
  • Events
No Results
View All Results
  • News
    • Contracts awarded
    • Open tenders and opportunities
    • Events
  • Features
  • Water
  • Wastewater
  • Gas
  • Electricity
  • Civil Construction
  • Events
No Results
View All Results
Home

How has HDD changed the way projects tackle shore crossings? Part 1

by Laura Harvey
August 7, 2017
in Civil Construction, Features, Pipelines, Trenchless technology
Reading Time: 4 mins read
A A
Share on FacebookShare on Twitter

In this article, the first of a two-part series, our HDD expert Charles Stockton takes a closer look at the impact HDD technology has had on shore crossings in pipeline installations.

Working in the nearshore environment, especially on Australia’s exposed coastlines, can be very challenging and inhospitable for both land-based and water-based construction equipment.

Neither construction method is ideally suited to construction in this shallow, tidal, high-energy zone; it is too shallow for marine vessels which risk grounding, and too deep and exposed for land-based work which risks flooding and equipment damage.

This is the zone that neither the offshore contractor or the onshore contractor are ideally placed to manage, it is not their normal working environment and it is this challenge that makes shore crossings very interesting to design and construct.

Up to 15 years ago, these crossings would have required large-scale open battered excavations onshore which would connect to a piled cofferdam through the surf zone followed by a dredged channel offshore. A concrete-coated pipe section would be floated into position using floatation devices and hydraulic winches.

The process was very susceptible to adverse weather conditions and tidal variations, as well as presenting numerous challenges for managing worker safety and potential damage to the environment including oil spills and erosion.

What are the benefits of using HDD for shore crossings?

By using HDD to construct the shore crossing, you are totally eliminating the requirement for works to be constructed in the nearshore environment.

Using HDD allows for the crossing length and depth to be increased, which positions the rig back on level land and also allows for the exit to be beyond the surf zone. The rig will be placed well behind the dune system, which can then be preserved to prevent erosion and maintain existing flora and fauna within the coastal corridor.

The exit point will be selected to provide appropriate conditions for positioning subsea structures or providing a suitable transition to offshore pipeline. The exit location must provide sufficient water depth to allow safe vessel access and anchoring as well as diving operations.

The pipelines can be prefabricated onshore and thrust through the bore from entry to exit, or alternatively, the HDD rig can be used to pull back the pipeline from offshore if the pipe is fabricated by a lay barge or towed offshore from a spool base/launching area.

This is particularly convenient if the product pipe is HDPE, which will float without the use of external buoyancy control measures.

What are the main challenges when using HDD for shore crossings?

One of the main challenges for designing an HDD shore crossing is selecting an appropriate exit location and then obtaining reliable, cost-effective geotechnical offshore information.

For shorter crossings, it may be possible to interpolate onshore and nearshore boreholes, but for longer crossings it is extremely important to develop an understanding at the exit topography and geology.

This is critical for developing the HDD methodology; determining whether the hole will be forward reamed or back reamed and if the pipe will be thrust or pulled into the bore.

Another key factor that needs to be carefully considered is weather. Even though the majority of the works can be conducted onshore, marine vessels and divers will still need to be deployed during a number of critical stages of the operation.

Having these windows well identified, and then having contingency planning for delays is essential. Clearly setting out what conditions the marine vessels can operate in and determining how this risk will be costed will be important to prevent cost escalation and potential disputes between parties.

In the next issue of Utility, Part 2 of this article will look at the differences in using HDD in water environments as opposed to standard environments; and some of the shore crossing projects Charles has been directly involved in.

 

Related Posts

Image: Water Corporation

Construction contracts awarded for Goldfields Pipeline upgrades

by Hayley Ralph
July 13, 2026

The $543 million upgrade of WA’s ageing Goldfields Pipeline has marked a major milestone with the awarding of contracts.  Western Australian Government has chosen contractors as part of the first...

It is hard to find asset defects from ground level. Image: RMIT University

RMIT expert warns of hidden grid pressures

by Hayley Ralph
July 13, 2026

Data centres are rapidly becoming one of the most significant new sources of demand on Australia’s electricity networks. Across several...

RIDGID’s SeeSnake performs 
non‑invasive pipe 
inspections. Image:  RIDGID

RIDGID marks 30 years in diagnostics

by Hayley Ralph
July 13, 2026

RIDGID, a part of global technology solutions provider Emerson’s professional tools portfolio, is celebrating its 30th anniversary in diagnostics. The...

Read our magazine

Join our newsletter

View our privacy policy, collection notice and terms and conditions to understand how we use your personal information.

Utility is the title of choice for decision makers at all levels of water and energy utilities, as well as other major players like consulting engineers and first-tier contractors. Utility is integrated across print and online, and explores the biggest news and issues across the utility industry. It is Australia’s only dedicated utility magazine, and covers all areas of the utility sector, including water and sewer, gas, electricity, communications and the NBN.

Subscribe to our newsletter

View our privacy policy, collection notice and terms and conditions to understand how we use your personal information.

About Utility

  • About
  • Advertise
  • Subscribe
  • Contact
  • Digital magazine
  • Events
  • Terms & Conditions
  • Privacy Collection Notice
  • Privacy Policy

Popular Topics

  • News
  • Water
  • Electricity
  • Projects
  • Water and Wastewater Treatment
  • Spotlight
  • Civil Construction
  • Renewable Energy

© 2026 All Rights Reserved. All content published on this site is the property of Prime Creative Media. Unauthorised reproduction is prohibited

No Results
View All Results
NEWSLETTER
SUBSCRIBE
  • News
    • News
    • Contracts awarded
    • Open tenders and opportunities
    • Events
  • Features
  • Water
  • Wastewater
  • Gas
  • Electricity
  • Civil Construction
  • Events
  • About
  • Advertise
  • Subscribe
  • Contact

© 2026 All Rights Reserved. All content published on this site is the property of Prime Creative Media. Unauthorised reproduction is prohibited