Share

A major electricity infrastructure milestone was recently achieved in Perth, with work complete on the long-planned Western Power Hay to Milligan Project – a critical piece of state electricity infrastructure that secures power supply in the CBD, helping to deliver a bright future for the city and the state.

Western Power is a State Government-owned corporation responsible for building, maintaining and operating an electricity network that connects 2.3 million customers in the southwest corner of Western Australia.

Part of the $37 million Western Power project was the installation of a 132kV underground cable circuit between the existing Hay Street Substation (HAY) and Milligan Street substation (MIL) in the Perth CBD – to meet N-2 CBD reliability requirements.

A ROI was released to the market in late 2016 followed by a tender process in 2017. Following in-depth negotiations, Daly’s Constructions was awarded the project in August 2018.

The contract was awarded on an EPC basis, with Daly’s responsible for:

• Final route verification and selection

• Approvals from all stakeholders

• Cable system detail design to achieve a 175MVA summer rating

• Procurement of all materials including 132kV power cable, cable joints, accessories and all civil construction materials

• Cable hauling

• Cable jointing and terminating

• Construction and installation

• Pre-commissioning tests & handover

Daly’s partnered with Taihan Electric Australia to deliver the project.

Challenges

Daly’s Constructions’ first project in Western Australia required detailed planning, especially involving mobilisation of resources, plant and equipment, as well as establishing suitable subcontractor and supplier arrangements.

In addition to working with Western Power, complex engagement, negotiations and approvals in the design phase were required from major stakeholders, including:

• Public Transport Authority

• Metropolitan Redevelopment Authority

• City of Perth

• Water Corporation of WA

• Main Roads WA

• ATCO Gas

One of the key challenges experienced during the project included: confirming a route that would satisfy third party approval requirements and minimise disruption to the CBD, whilst achieving the required circuit rating where the circuit is to be installed in close proximity to existing 132kV feeders.

Almost 400 existing underground services along the 2km route, ranging from large storm water and rising sewer mains, to live power cables, HP gas mains and strategic optic fibre cables, were traversed with zero damages.

One of the more challenging road crossings was the Hay St and Milligan St intersection. This road crossing was completed over a weekend commencing on Friday evening, running back-to-back crews for 60 hours through to the Monday morning.

This involved the removal of oil filled 132kV cables and asbestos conduits, excavating at 2.7m depth in sand using shoring boxes adjacent to live traffic whilst crossing some 15 live services.

Other key challenges included:

• Multiple major crossings along the route: rail, major roads, ATCO gas, critical optic fibre cable, major public area

• The requirement that the road network was to be available at the completion of each night shift to enable normal traffic flows, thus limiting disruptions to the road network and the public. This was the first time this methodology was engaged on a transmission project in central Perth

• Two precast concrete joint bays were designed and manufactured, each weighing 24 tonnes

• Minimising community and business disruption: vehicle and pedestrian traffic, rail services, the Perth Arena, Art Gallery of WA, the State Theatre Company, hotels, cafes, use of predominantly night works, numerous car park access points, access between the CBD and Northbridge entertainment precinct

• Significant structural modifications to existing walls and floors within both substations required to facilitate cable and switchgear installation on the third level

• Complex environmental issues involving the testing, management and disposal of significant groundwater and acid sulphate soils, as well as archaeological and heritage aspects required liaison, monitoring and approvals

• Interface and coordination with Western Power’s GIS switchgear installation in Milligan St Substation

• The unprecedented COVID impacts that adversely affected the delivery and installation of key components

Project highlights

Western Power Project Manager, Ian Anderson, said one of the big successes of the project has been a new technique to lay the cable conduits in short sections in high traffic areas, reducing the impact on commuters.

“Each night, Daly’s excavated a short section of the route, say 20m, laid the conduits, installed thermal backfill and added fresh asphalt, ready to be driven over the next morning. It’s been a new way of working for us which worked really well.

“The disruption to everyday life in the CBD was incredibly minimal given the importance of the route we are taking and it has saved a huge amount of costs in traffic management.”

The project’s safety performance was outstanding, with no recordable incidents during the construction phase. Two sleeve bores under the Perth metro rail system either side of the Perth train station were also a highlight. These were achieved after prolonged negotiations with the PTA and the minimal construction window approved for each shift.

The drill shots were six metres deep with significant groundwater to manage.

Another success was the cable installation in an urban environment and up four levels in existing substations, as well as the cooperative and outcome-driven approach between Western Power and Daly’s facilitating the successful delivery of the project.

“The success of the project delivery is due to the collaborative approach with Western Power’s project team, major stakeholders, effective planning and Daly’s highly committed workforce,” Daly’s Director, Malachy Daly, said.

“This project was one of Daly’s Construction’s most challenging undertakings and relied heavily on some of our most experienced people to deliver it.”

Long-term benefits

• Modifications and enhancements to the Western Power transmission specification from project experiences and the effective implementation on this project

• The now demonstrated methodology of ensuring the road network is available at the conclusion of each night shift for future transmission underground projects

• Daly’s are well positioned in the Western Australia market to leverage off the excellent outcomes from this project

This Sponsored Editorial was brought to you by Daly’s Constructions.

For more information, contact Daly’s Constructions at [email protected] or visit www.daly.net.au.

©2024 Utility Magazine. All rights reserved

CONTACT US

We're not around right now. But you can send us an email and we'll get back to you, asap.

Sending

Log in with your credentials

Forgot your details?