Share

More than two years after mobilisation, microtunnelling specialist Rob Carr successfully overcame multiple hurdles and delivered their largest and longest running contract—the Microtunnelling & Civil Works subcontract for Green Square Stormwater Drain Project in metropolitan Sydney.

Green Square is one of the City of Sydney’s key urban renewal precincts, which is in the process of being transformed from old industrial land into a major new residential, retail and cultural hub. By 2030, the broader Green Square Urban Renewal Area is expected to accommodate approximately 61,000 residents and 22,000 workers.

The Green Square town centre is located on a floodplain known as the Waterloo Swamp, and the new two kilometre stormwater drain is needed to reduce hazardous flooding in and around the town centre and enable further development.

The project is in its final stages, and being delivered by the Drying Green Alliance (comprising client partners Sydney Water and City of Sydney with UGL Engineering, Parsons Brinkerhoff,
RPS Manidis Roberts and Seymour Whyte Constructions).

Rob Carr, as a related party entity to sister company Seymour Whyte Constructions, worked closely with the Alliance partners in 2014 during the Expression of Interest and Target Outturn Cost stages to submit a competitive bid for the project.

Rob Carr Construction Manager, Iain Lamb, said the company was heavily involved in the detailed design phase for both the stormwater pipelines and box culverts.

“The tender reference design primarily consisted of box culverts installed by open cut methods, which would have required larger, more disruptive site footprints, multiple service diversions and major road closures with larger volumes of spoil and dewatering to dispose of,” Mr Lamb said.

“Our trenchless solution offered an alternative, value for money approach with significantly reduced environmental impact and comparatively minimal community disruptions.”

Following the successful tender process, the Drying Green Alliance was given preferred status in December 2014.

The Alliance team mobilised the following month with the Project Alliance Agreement executed in mid-February 2015.

The Rob Carr team mobilised in April 2015 and by the time they completed the work in mid 2017, their scope of works had extended to include:

  • Four kilometres of DN1800 microtunnelling using concrete jacking pipe
  • Five caissons varying in diameter between 10–12m, and in depths up to 10m
  • Eight other conventionally shored shafts up to 6m deep construction of a DN840 watermain and DN225 open trench sewer including several concrete manholes up to five metres deep
    Construction of permanent complex civil structures within each of the caissons supervision and management for all works within
    the microtunnelled sections of the project
  • The project site was located on a floodplain and was once a network of swamps, wetlands and creeks, which caused Rob Carr’s biggest challenge over the contract duration, working in high water table ground that was classified as restricted and hazardous.

For 20 months, the Rob Carr team worked to install DN1800 concrete drainage pipeline via microtunnelling in twin and triple parallel formation over a 1.3km section through poor subsurface ground, which consisted of fill and loose wet sand.

Project Manager, Darren Madden, said that working in such difficult ground conditions required diligent planning and team commitment.

“Our team performed well under pressure. Whenever we came up against an unexpected challenge, our team would always come up with a Plan B to pull together and solve the issue.”

Mr Madden highlighted a recent incident where a tunnel boring machine (TBM) was blocked due to buried steel objects and could not proceed further.

“To complete the work, our team sank 7.3m shoring boxes down to six metres and drove sheet piles outside the shoring box panels to project downward between the new and existing previously tunnelled line,” Mr Madden said.

“This enabled the removal of the obstruction, which in this particular case was a section of steel plate buried in sand six metres deep. Following this, the TBM was retrieved and re-launched from the opposite end to complete the line.

“This was typical of the type of obstructions that were encountered along the alignment—there could be 200m of clean natural sand, then in one localised position a buried object would prevent the TBM from continuing. Unfortunately, this is impossible to predict even with the most detailed geotechnical information.”

To facilitate the trenchless pipeline installation, Rob Carr Pty Ltd self-performed the construction of five in situ concrete caissons between 10m and 12m in diameter in critical locations as well as eight other conventionally constructed shafts. This allowed for tunnelling equipment access and recovery, and enabled the team to construct other key complex drainage infrastructure.

With the range of multi-disciplinary work and extended scope of works that Rob Carr had to self-perform, Construction Manager, Iain Lamb, said the team increased to more than 50 employees at peak of construction.

“Our project team consisted of TBM operators, pit men, dogmen, general labourers, plant operators, trades such as carpenters, pipelayers, formworkers and boilermakers, supervisors and engineers,” Mr Lamb said.

“To ensure we had the right resources to carry out the works efficiently and safely, we invested time in recruiting quality new personnel to supplement our existing experienced team.”

Through good leadership on the ground by the experienced team members, Rob Carr was able to integrate the new members of the workforce while adhering to the highest safety and quality standards at all times.

Rob Carr constructed three parallel lines, only 800mm apart, in a curved alignment

Project Manager, Darren Madden, said that although time and production schedules were tough, safety remained the top priority for the team.

“Our team takes a proactive approach to safety, and we look to eliminate risk or engineer a solution to reduce risk. A recent example involved planning for the lifting of roof beams for a 6m x 6m cast in-situ pit, it was highlighted that it would introduce a working at heights risk for the person removing the chains after the lift,” Mr Madden said.

“Our Supervisor Damian Coward devised the solution of installing handrails on the precast beams prior to lifting them to eliminate the risk of working at heights.”

Rob Carr General Manager, Angelo Soumboulidis, described the Green Square Stormwater Drain Project as the company’s largest contract, and possibly its most challenging, to date.

“This project has showcased Rob Carr’s ability to step up and face challenges head-on to produce successful results. I commend every one of our project team—from workers to supervisors and managers—for their perseverance on this complex project,” Mr Soumboulidis said.

“The team had to contend with difficult ground conditions, brownfields sites full of buried man-made objects in the fill ground, time pressures and multiple constrained project sites, often next to live traffic or other works.

“Yet with all of this, the team never gave up and work was completed on budget and on time.”

About Rob Carr 

Rob Carr is recognised as a leader in civil construction and tunnelling. Our specialist services include microtunnelling, detailed excavation and caisson construction, pipelines, pump station construction, complex concrete structures, mechanical and electrical works and rehabilitation. Rob Carr’s multi-disciplinary offering delivers efficiencies for clients who need a wide range of
utilities services and turnkey solutions.

In October 2017, Rob Carr and the Seymour Whyte Group joined VINCI—a global player in concessions and construction that employs more than 183,000 people in some 100 countries. As part of VINCI, Rob Carr will have access to international expertise and innovations that will enhance our in-depth local knowledge.

This partner content is brought to you by Rob Carr. For more information, visit www.robcarr.com.au.

Lauren ‘LJ’ Butler is the Assistant Editor of Utility magazine and has been part of the team at Monkey Media since 2018.

After completing a Bachelor of Media, Communications and Professional Writing at the University of Wollongong in 2014, and prior to writing about the utility sector, LJ worked as a Journalist and Sub Editor across the horticulture, hardware, power equipment, construction and accommodation industries with publishers such as Glenvale Publications, Multimedia Publishing and Bean Media Group.

©2024 Utility Magazine. All rights reserved

CONTACT US

We're not around right now. But you can send us an email and we'll get back to you, asap.

Sending

Log in with your credentials

Forgot your details?