Essential wastewater infrastructure will be upgraded in the Queensland suburb of Loganlea.
Project works commenced on 6 January 2020 on Loganlea Road and will include the installation of about 20m of wastewater pipeline, a maintenance hole and associated infrastructure.
Construction will be in the centre of the road outside 60 and 66 Loganlea Road, and traffic will be reduced to one lane for the duration of the works.
While every effort will be made to minimise disruption to residents and drivers, impacts may include:
- Increased levels of noise and dust
- Restricted pedestrian access along Loganlea Rd
- Clearing of vegetation
- Regular truck movements for delivery/removal of materials
Construction will be between 7am and 5pm Monday to Friday, but some night or
weekend work may be required.
The upgrade is expected to be complete in February 2020.